1434 W. Fillmore – Reaching New Heights in Construction
At 4Corners, we take pride in building spaces that contribute to the fabric of Chicago’s communities. Our 1434 W. Fillmore project is advancing rapidly, with major structural and interior milestones achieved in recent weeks.
Latest Progress at 1434 W. Fillmore
We’re making significant strides toward completion, with key construction updates including:
- 5th-floor trusses installed – The building is now reaching its full structural height.
- Indoor framing complete on floors 1-3 – Interior spaces are taking shape, defining future residences and commercial areas.
- Windows installed on floors 1-3 – A major step in sealing the building while enhancing aesthetics and energy efficiency.
- Mechanical, electrical, and plumbing (MEP) started on floors 1-3 – Critical infrastructure is now being integrated.
Each milestone brings us closer to delivering a high-quality development that will enhance the Fillmore community.
See It for Yourself
To capture the transformation of 1434 W. Fillmore, we’ve documented progress with exclusive drone footage—providing a bird’s-eye view of how this project is evolving.
Watch Now.
What’s Next?
With these foundational elements in place, the next phase of development will focus on:
- Advancing MEP installations throughout the building.
- Completing exterior finishes to bring the project’s design to life.
- Preparing for interior build-outs to make this space move-in ready.
Stay tuned as we continue shaping the future of 1434 W. Fillmore—one milestone at a time.